The NYC Energy Conservation Code establishes the minimum energy performance for buildings, and commissioning becomes mandatory in projects that meet certain conditions described in the code. In these cases, commissioning must follow an established procedure and specific documentation requirements.
Normally, the energy code only applies for new constructions and for existing buildings that undergo a major change or renovation. The code does not impose energy retrofits on existing buildings, except in cases where a local law mandates a specific upgrade. An example of this is Local Law 88, which requires code-compliant lighting upgrades for all buildings under its coverage by 2025.
The mandatory commissioning requirements in the energy code are for commercial buildings. However, note that high-rise multifamily constructions are considered commercial under the energy code. Only the following building types are subject to the residential requirements:
If a property is used for residential purposes, but it does not meet any of the conditions above, it is subject to the commercial requirements of the NYC energy code. In many cases, this includes a mandatory commissioning procedure.
Buildings subject to commissioning under the NYC Energy Code must follow the procedure described in section C408. Even if all building systems are installed correctly, the project cannot pass the final inspection unless the owner provides evidence of commissioning by an approved agency.
The first step is developing a plan to guide the process. This plan must be written by an approved agency, covering the following points:
HVAC systems involve airflow, and many configurations also use water to transport thermal energy. To deliver heating and cooling effectively, these air and water flows must be balanced. The NYC Energy Code requires adjustment and balancing according to ASHRAE 111 or any equivalent standard approved by the NYC Department of Buildings.
Balancing means are not mandatory for equipment below certain capacity thresholds: fans with motors up to 1 hp, and pumps with motors up to 5 hp. Pumps are also exempt from balancing if throttling does not increase losses by more than 5%, with respect to the power drawn with a trimmed impeller.
As its name implies, this step ensures building systems are properly installed and configured, so they can offer the performance specified in the design documents.
The preliminary commissioning report accomplishes two main functions:
Once the preliminary commissioning report is delivered to the building owner, and the corresponding code official is notified formally with a letter of transmittal, the building can be subject to the final inspection process.
The system balancing report provides a detailed description of the adjustment and balancing procedure for air and hydronic systems, including the measurements carried out.
Once all deficiencies and pending tests identified in the preliminary commissioning report have been corrected, the final commissioning report can be written and delivered. After a building receives the certificate of occupancy or letter of completion, there is a deadline for final report delivery, which changes based on building conditions:
Commissioning is a challenging procedure due to the variety of building systems involved, and your building cannot receive a final inspection until you complete commissioning and its preliminary report. However, this is not an issue if you work with qualified professionals who are familiarized with NYC code requirements and the corresponding documentation. As a property developer, it is in your best interest to avoid a long approval process, since it delays tenant occupancy and payments.