CHALLENGES

Jet’s Pizza was planning to open a new store in Florida. The place was a small white box space with existing electrical, water, sanitary, and gas services provided by the base building.

The client was looking for a low-cost design by utilizing the existing services provided by the base building.

Following were the challenges-  

  1. Design the MEP system using existing base building services.
  2. Fit the complete system within a small space.
  3. Running the services from the existing service location to the new space by keeping the other existing commercial stores operational.

jetspizza

SOLUTION

Our team of engineering design experts took the challenge and found the best possible routing for the gas and water piping without affecting the operations of other adjacent stores. Water, gas, and electrical power load were calculated and satisfied within the available existing load in compliance with all local and energy conservation requirements. Wall-mounted tankless water heater was provided to reduce the equipment space.

We saved the cost and time for the client by providing a quick, affordable, and error-free design within 2 weeks which resulted in quick approvals and set-up of the new Jets pizza.

Scope includes plumbing, sprinkler, HVAC & electrical.